How to Install Steel Rebar in Concrete: Step-by-Step
How to Install Steel Rebar in Concrete
Last updated:
Read bending schedules, place bars per drawing, tie with wire, maintain cover. Lap lengths, spacer placement, Building Control inspection prep. B500B rebar from £2.50.
| Field | What It Tells You | Example | Common Mistake |
|---|---|---|---|
| Bar mark | Unique ID for each bar type in the drawing | 01, 02, 03 | Mixing up marks — placing mark 02 where mark 03 goes |
| Shape code | BS 8666 standard shape (straight, L, U, cranked) | 20 = straight, 32 = L-bar, 38 = U-bar | Bending a code 20 (straight) bar on site because the wrong mark arrived |
| Diameter (mm) | Bar size: T8, T10, T12, T16, T20, T25, T32, T40 | T16 = 16 mm diameter | Installing T12 where T16 is specified — 44% less steel area |
| Number required | Total count of that bar mark for the element | 24 No. | Ordering 24 but only installing 20 — leaves gaps in the reinforcement |
| Cutting length (mm) | Total straight length before bending | 3,200 mm | Confusing cutting length with finished dimension after bending |
| Bending dimensions | Dimensions A, B, C etc. per shape code | A=300, B=2600, C=300 | Swapping A and C dimensions — bar fits but cover is wrong at one end |
| Element | Bar Size | Typical Spacing | Direction | Cover (mm) |
|---|---|---|---|---|
| Ground-bearing slab (domestic) | T12 or A393 mesh | 200 mm centres | Both ways | 40–50 (bottom) |
| Suspended slab | T16 at 150–200 centres | 150–200 mm | Bottom mat both ways, top at supports | 25–35 |
| Strip foundation | T12 or T16 | Per engineer’s schedule | Longitudinal + links | 40–50 |
| Pad foundation | T16 or T20 | 150–200 mm | Both ways, bottom mat | 50–75 |
| Beam (300–450 mm deep) | T16–T25 main bars | Per schedule | Main bars bottom + top, links at 150–250 centres | 25–35 |
| Column (300 × 300 mm) | 4×T16 or 4×T20 main bars | Per schedule | Vertical mains + T8 links at 200–300 centres | 25–35 |
| Mistake | What Happens | How to Prevent | Cost If Caught Late |
|---|---|---|---|
| Wrong bar diameter | Structural capacity reduced — T12 has 113 mm² vs T16 at 201 mm² | Check diameter with vernier callipers against schedule | Strip out and replace: £500–£2,000+ |
| Insufficient lap length | Bars cannot transfer load across the joint — lap fails | Lap = 40× diameter minimum (640 mm for T16) | Strip out and re-fix: £300–£1,500 |
| Bars in wrong position | Moment capacity wrong — bottom bars at top or vice versa | Read drawing orientation marks (B = bottom, T = top) | Strip and reposition: £500–£3,000 |
| Missing spacers | Cover too thin — corrosion in 15–20 years instead of 50+ | Place spacers at 500 mm max centres before tying | Rejected by Building Control — delay + rebooking |
| Links not closed | Beam or column links open at top — confinement lost | Tie both ends of every link with wire | Re-tie before pour or Building Control rejection |
| Mesh not lapped | Mesh sheets butted with no overlap — no load transfer | Lap mesh by minimum one full opening (200 mm for A393) | Remove concrete if already poured: £5,000+ |
How Do You Read a Bar Bending Schedule?
The bar bending schedule is the instruction sheet for every bar on site. It lists each bar by mark number, shape code (per BS 8666:2020), diameter, number required, cutting length, and bending dimensions. Mark 01 might be 24 No. T16 straight bars at 3,200 mm cutting length. Mark 02 might be 12 No. T12 L-bars with dimensions A=300, B=2,600.
Shape codes are standardised. Code 20 is a straight bar. Code 32 is an L-shape (one 90° bend). Code 38 is a U-bar (two 90° bends). Code 51 is a cranked bar. The shape code tells the bending machine exactly what shape to produce. NextDaySteel cuts and bends to BS 8666:2020 — every bar matches the schedule dimensions within standard tolerances (±5 mm on lengths up to 1,000 mm, ±5 mm + 1 mm per additional metre).
Cross-reference the schedule against the structural drawing before delivery. Count the marks, check diameters match the drawing annotations, and confirm the number of bars per mark. Keira Graham reviewed: “Reinforcement schedules were thoroughly checked by staff to make sure we had got everything we needed.”
How Do You Place Rebar According to the Drawing?
The structural drawing shows bar positions in plan and section views. Each bar mark has a location: bottom mat, top mat, near face, far face. The drawing indicates spacing (e.g., T16-200 B means T16 bars at 200 mm centres in the bottom). Start from the reference point on the drawing — usually a grid line or wall face.
For a slab bottom mat, lay the first bar 100 mm from the edge (half the spacing for 200 mm centres). Place subsequent bars at 200 mm centres using a tape or pre-marked spacer bar. The long-span bars go down first, short-span bars on top. This layering order affects the effective depth — the bottom layer carries more load, so the engineer specifies which direction goes first.
For beams, the main bottom bars sit in the corners of the links. Thread the main bars through the links before tying. Position the links at the spacing shown on the drawing — typically 150–250 mm centres, closer near supports where shear is highest. Each link should be vertical and square to the beam axis.
What Is the Correct Way to Tie Rebar with Wire?
Use 1.6 mm black annealed tie wire. Cut 300 mm lengths or use a wire reel with a tying tool. The standard tie is a snap tie (single loop): wrap the wire diagonally around the intersection of two bars, twist the ends together 3–4 turns with pliers or a tying hook, then snap off the excess. The twist should be tight enough that the bars do not move when you push them.
Tie at every second intersection on slabs (chequerboard pattern). Tie every intersection on beams, columns, and any reinforcement cage that will be lifted. On wall reinforcement, tie every second horizontal-vertical crossing on each face, plus every intersection at the bottom 500 mm where bars are most likely to shift during the pour.
Do not over-tie — it wastes time without adding strength. Do not leave long wire tails sticking out toward the formwork face. Wire tails within the cover zone create a corrosion path from the surface to the bar. Bend all tails inward, away from the nearest concrete surface. NextDaySteel supplies tie wire with rebar orders.
How Do Spacers Maintain the Correct Cover Depth?
Spacers hold the reinforcement at the correct distance from the formwork face. The engineer specifies cover depth per BS 8500 — typically 25 mm for internal dry conditions (XC1), 35–45 mm for external (XC3/XC4), and 50 mm+ for ground contact or coastal (XC2/XS1). Use spacers that match the specified cover height exactly.
Place spacers at maximum 500 mm centres on horizontal bars, 1,000 mm on vertical bars. Use concrete spacers for ground-contact elements (foundations, ground-bearing slabs) and plastic clip spacers for above-ground elements (beams, columns, walls). NextDaySteel supplies spacer packs at £12.00 per pack — add them to your rebar order for one delivery.
Check cover with a cover meter before the pour. Press the meter against the formwork and it reads the distance to the nearest bar. If any reading is below the drawing specification, add or adjust spacers. Building Control may bring their own cover meter to the pre-pour inspection. A 5 mm shortfall in cover can cut 10–15 years off the reinforcement’s protected life in external elements.
What Does Building Control Check Before the Pour?
Building Control inspects reinforcement against the approved structural drawings. They check: bar diameters match the schedule, bar spacing matches the drawing, lap lengths meet the minimum (typically 40× bar diameter for tension laps in B500B steel — 640 mm for T16), cover depth is correct via spacer check or cover meter, links are tied and closed, and the cage is rigid enough to survive the pour without displacement.
Common reasons for rejection: wrong bar diameter (T12 installed instead of T16), insufficient laps (bars overlapping 300 mm instead of 640 mm), missing links in beams or columns, spacers too far apart or wrong height, mesh sitting on bricks instead of proper spacers, and reinforcement not matching the approved drawing revision.
If Building Control rejects the reinforcement, the pour is cancelled. Fix the defects, rebook the inspection, rebook the concrete truck. Colin Berry reviewed NextDaySteel: “Had what I needed, right price, right quality, could meet my delivery date.” Right quality means B500B grade rebar to BS 4449:2005+A3:2016, CARES certified, cut and bent to BS 8666:2020.
Frequently Asked Questions
What tools do I need to install rebar?
A tape measure, tying hook or reel-type tying tool, 1.6 mm black annealed tie wire, side cutters, vernier callipers (to check bar diameter), and spacers matching the specified cover depth. For large cages, a rebar bender for minor site adjustments and a cover meter to verify depth before the pour. NextDaySteel supplies tie wire and spacers alongside your rebar order.
How long should rebar laps be?
For B500B steel in tension zones, the minimum lap length is 40× the bar diameter. T12 = 480 mm, T16 = 640 mm, T20 = 800 mm. In compression zones, 30× diameter is common. The engineer specifies exact laps on the drawing — these may be longer than the minimum depending on concrete grade, bar spacing, and cover. Always follow the drawing, not just the minimum rule.
Do I tie every rebar intersection?
Not always. For flat slabs, tie every second intersection in a chequerboard pattern — this holds the bars in position during the pour. For beams, columns, and any cage that will be lifted by crane, tie every intersection. For walls, tie every second crossing on each face plus every intersection in the bottom 500 mm where bars are most likely to shift.
What happens if Building Control rejects my rebar?
The pour is cancelled. You fix the defects (wrong bars, short laps, missing spacers), rebook the Building Control inspection, and rebook the concrete truck. A cancelled domestic pour wastes £700–£1,500 in concrete, labour, and rebooking fees. Check everything against the drawing yourself before calling the inspector. If you need replacement bars, NextDaySteel delivers next working day for orders before 1pm (£90).
Can I bend rebar on site?
Minor adjustments only. BS 8666:2020 sets minimum bend radii per diameter — T12 minimum mandrel 48 mm, T16 minimum 64 mm. Bending tighter than the standard weakens the steel at the bend. For scheduled bars, order cut and bent from NextDaySteel to BS 8666:2020. T12 at £5.97 per 6 m length, T16 at £10.95 per 6 m. Factory bending is more accurate than site bending.
How do I fix links and stirrups in beams?
Thread the main bottom bars through all the links first, then spread the links to the correct spacing (per the drawing, typically 150–250 mm centres). Tie each link to the main bars at all four corners. Place top bars inside the links and tie them. Close the link hooks by bending the tail around the top bar and tying it. Every link must be closed — open links lose confinement.
Customer Reviews
4.8/5 from 170 Google reviews"On-time delivery. Great customer service."
"fast delivery very good price . highly recommend"
"We recently purchased reinforcement from Next Day Steel and are very pleased with the service. Their quick response, competitive prices, and next-day delivery options are excellent."

